新能源總承包工程項目調試管理研究
陸冉,袁龍威
(中國能源建設集團江蘇省電力設計院有限公司,江蘇 南京 211102)
摘 要:新能源成為我國電力的發展方向,站內設備調試及涉外設備調試是重要的一個環節,通過高壓試驗、保護調試、回路的傳動,來保證受電前設備及施工的質量。結合已開展的新能源總承包項目,基于新能源電站并網拓撲結構,針對調試范圍進行劃分,討論了如何運用項目管理手段實現對調試環節的“質量、成本、進度“三要素管理,來有效提升調試管理質量。
關鍵詞:新能源;調試;項目管理;三要素管理
中圖分類號:TM61;TM734 文獻標識碼:A 文章編號:1007-3175(2020)04-0064-04
Research on Commissioning Management of New Energy General Contracting Projects
LU Ran, YUAN Long-wei
(China Energy Engineering Group Jiangsu Power Design Institute Co., Ltd, Nanjing 2111 02, China)
Abstract: New energy has become the development direction of electric power in China. The station equipment debugging and the foreign-related equipment debugging are the most important links. The quality of equipment and construction before electricity was ensured through the high-pressure test, the protection debugging and the loop transmission. Combining with the new energy general contracting project carried out by our hospital, based on the grid connection topological structure of the new energy power station and aiming at the debugging range division, this paper discussed how to use project management means to realize the “quality, cost and schedule” management to effectively promote the quality of debugging management.
Key words: new energy; debugging; project management; three elements management
參考文獻
[1] 任鐘淳,蕭能意,韓濤. 電力工程項目管理的模式探討[J]. 中國勘察設計,2003(4):33-38.
[2] 關宇, 廖麗貞, 董哲, 等. 新能源升壓站監控系統調試方法研究[J]. 自動化應用,2017(5):141-142.
[3] 胡巖,賈冰. 電力工程項目管理的三要素分析[J].東北電力大學學報,2008,28(3):1-3.
[4] 閆培麗,袁兆祥,齊立忠,等. 海上風電場二次系統設計關鍵技術[J]. 電力建設,2015,36(4):129-133.
[5] 張哲. 東海大橋100 MW海上風電場電氣系統的設計[J]. 電力與能源,2012,33(1):49-51.
[6] 楊明,宋曉兵. 風電場升壓站電氣設備安裝調試管理[J]. 云南水力發電,2016,32(4):22-24.
[7] 張馳. 風電場升壓站電氣設備安裝與調試探究[J].科技風,2018(4):163.
[8] 尹佳林. 風力發電廠設備調試過程管理現狀與問題[J]. 黑龍江科技信息,2011(27):65.
[9] 何建軍,趙飛,馮磊華,等. 基于WMCS的大型風電場群遠程監控系統協調運行調試研究[J]. 風能,2016(10):58-61.